Construction of 220/132/66 KV Substation at Ghoda Chhaka Bhuban.

Duration: Aug 2018 to Jan 2020

132KV Transmission Line at Kennapali Grid Sundargarh to Vedanta Ltd Plant @ Jharsugura

Duration:July 2017 to Dec 2017

132KV Transmission Line at Udala OPTCL Grid Construction to Balesore Lilo Point

Duration: July 2017 to Dec 2017

Construction & Installation of 33/11KV Gis Sub-Station Under Optcl Unit 8, Bhubaneswar

Duration: March 2020 Jan 2023

Construction & Installation of 33/11KV Gis Sub-Station Under Optcl Bjb Nagar, Bhubaneswar

Duration: March 2020 Aug 2022

Construction & Installation of 33/11KV Gis Sub-Station Under Optcl Bapuji Nagar, Bhubaneswar

Duration: Oct 2020 to Nov 2023

Construction & Installation of 33/11KV Gis Sub-Station Under Optcl Saheed Nagar, Bhubaneswar

Duration: Oct 2020 Dec 2023

Installation of 10/12.5 MVA, 132/11 KV Transformer with OLTC for IREL Chatrapur Odisha

Duration: On Going from Dec 2019